# Batching: Consolidation, Piece Labeling & Sequencing

![](/images/csdirector-cstruss/images/icons/d-videossttraining.png) **Watch video**

**Summary**

After a project has been designed and met engineering requirements, the next step is to produce the trusses. The batching process lets you group and package truss components for production. This includes gathering the required lumber, cutting and labeling boards, and assembling trusses.

**Window**

1. Navigate to **Presets** > **Fabrication** > **Piece Labeling and Sequencing**.


The window shown below is used to define different options for batch processing.

![](/images/csdirector-cstruss/images/d-piecelabelingandsequencing-1059x697.png)

**Field Descriptions**

| Section/Field | Description |
|  --- | --- |
| Process Unit section | Controls saw file consolidation including cutting and saw table output. See [Presets](/csdirector-cstruss/help-center/director-online-help/presets/d-presetssettings) for additional Consolidation information. |
| Cutting Output Consolidation By:
 | Cutting output consolidation for saws.
Select one of the following:
- Project: Consolidates like pieces for output across the entire project
- Production Group: Consolidates like pieces for output by production group
- Truss: Consolidates like pieces for output by truss
- Same Piece: Only consolidates pieces in exact same position in multi-ply trusses
- Stack List by Plan/Elevation: Consolidates like pieces for output by stack list
- Stack List by Lot: Consolidates like pieces for output by stack list lots
- By Piece Type: Select from a list of Piece Types, each with a dropdown to select from a consolidation list .
- Truss By Truss: Multi-ply trusses will be listed in ply order (the front ply first to the back ply) unless sort order changes what is considered the first ply. See [Truss By Truss Consolidation](/csdirector-cstruss/help-center/director-online-help/batching/truss-by-truss-consolidation-example) for additional information.

 |
| Table Output Consolidation By | See [Presets](/csdirector-cstruss/help-center/director-online-help/presets/d-presetssettings) for detailed information about Table output. |
| **Piece Labeling and Sequencing** |  |
| Piece Label Prefix
 | Determines what character displays before the Piece Label Sequence Number.
Select the option for formatting the Piece Label Prefix:
- Custom Prefix per Piece Type
- First {x} Character(s) in Group Name
- Custom Prefix for All
- TBWGO

![](/images/csdirector-cstruss/images/d-piecelabelprefix.png)
 |
| Custom Prefix per Piece Type
 | Independently specify the label for each piece type.
- Top Chord: T
- Top Chord Overhang: T
- Bottom Chord: B
- Web: W
- Top Scab: T
- Bottom Scab: B
- Wedge: W
- Gable: G
- Other: O
- Slider: W

![](/images/csdirector-cstruss/images/d-customprefixperpiecetype.png)
 |
| First {x} Character(s) in Group Name
 | Select the number of leading characters in group names to be used as the label prefix.
![](/images/csdirector-cstruss/images/d-firstcharacteringroupname.png)
 |
| Custom Prefix for All
 | Specify a prefix to be used as the piece label prefix for all piece types.
- If the Prefix is left blank, the label only contains a sequence number.

![](/images/csdirector-cstruss/images/d-customprefixforall.png)
 |
| TBWGO
 | The following labels are used for each piece type.
- T = top chords, stacked top chords and top chord scabs
- B = bottom chords, stacked bottom chords and bottom chord scabs
- W = webs and wedges
- G = gables
- O = other

![](/images/csdirector-cstruss/images/d-tbwgo.png)
 |
| Piece Sequencing
 | Lets you determine when to restart the sequence number.
![](/images/csdirector-cstruss/images/d-piecesequencing-795x212.png)
 |
| Restart Sequence At
 | Select the option for when to restart the sequence number:
- Project: The sequence number will restart at 1 for each project; T1, B2, W3, G4… If the Restart per Piece Type checkbox is also selected then the sequence number will restart at 1 for each piece type; T1, B1, W1, G1… and will restart again at 1 for each project.
- Group: The sequence number will restart at 1 for each group; T1, B2, W3, G4… If the Restart per Piece Type checkbox is also selected then the sequence number will restart at 1 for each piece type; T1, B1, W1, G1… and will restart again at 1 for each group.
- Truss: The sequence number will restart at 1 for each truss; T1, B2, W3, G4… If the Restart per Piece Type checkbox is also selected then the sequence number will restart at 1 for each piece type; T1, B1, W1, G1… and will restart again at 1 for each truss
- None: The sequence number will not restart; T1, B2, W3, G4...
- Cutting Output Consolidation: The sequence number will restart at 1 for each Cutting Output Consolidation (project, group, truss or same piece); T1, B2, W3, G4… If the Restart per Piece Type checkbox is selected there will only be one T1, B1, W1, G1… within the selected Cutting Output Consolidation selection (group, project, truss, same piece

![](/images/csdirector-cstruss/images/d-restartsequenceat.png)
Restart per Piece Type
![](/images/csdirector-cstruss/images/d-restartperpiecetype.png)
The sequence number restarts at 1 for each piece type; T1, B1, W1, G1… and will reset again for the selected Piece Sequence Reset option.
- Checked (i.e. T1, B1, W1). This should be selected to work with the Left to Right or Right to Left Chord and Web Labeling options.
- Unchecked (i.e. By group T1, B2, W3).

 |
| Chord Labeling Sequence
 | Controls the sequence number order of chords.
Select one of the following options:
- Based on Saw Sort Criteria (i.e.first cut board would get #1 ): Chord sequence order will be based on the order that each piece falls in the saw sorting criteria.
- Left to Right Position on Truss: Only works if Restart per Piece Type is selected. All trusses will label based on the selected Chord Label Sequence setting.
- Right to Left Position on Truss: Only works if Restart per Piece Type is selected. All trusses will label based on the selected Chord Label Sequence setting.

![](/images/csdirector-cstruss/images/d-chordlabelingsequence.png)
Outside in when symmetric
![](/images/csdirector-cstruss/images/d-outsidewhensymmetric.png)
When Outside in when symmetric is checked, the chord sequence order will be based on the outside to center position of the truss.
It is recommended to use the same setting for Chord Labeling Sequence and for Web Labeling Sequence.
 |
| Web Labeling Sequence
 | Controls the sequence number order of webs.
Select one of the following options:
- Based on Saw Sort Criteria (i.e.first cut board would get #1 ): Web sequence order will be based on the order that each piece falls in the saw sorting criteria.
- Left to Right Position on Truss: Only works if Restart per Piece Type is selected. All trusses will label based on the selected Web Label Sequence setting.
- Right to Left Position on Truss: Only works if Restart per Piece Type is selected. All trusses will label based on the selected Web Label Sequence setting.

![](/images/csdirector-cstruss/images/d-weblabelingsequence.png)
Inside out when symmetric
![](/images/csdirector-cstruss/images/d-insideoutwhensymmetric.png)
When Inside out when symmetric is checked, the web sequence order will be based on the center to outside position of the truss.
It is recommended to use the same setting for Chord Labeling Sequence and for Web Labeling Sequence.
 |
| Piece Label Consolidation
 | Controls which pieces can be consolidated. This is for labeling only; saw output consolidation is not affected.
Select the option to specify which pieces to consider when consolidating like pieces:
- Consolidate by Project: Consolidates labels across the project and is not controlled by the saw file.
- Consolidate by Group: Consolidates labels across the group and is not controlled by the saw file.
- Consolidate by Truss: Consolidates labels across the truss and is not controlled by the saw file.
- No Consolidation.
- Cutting Output Consolidation: Consolidation matches the Process Unit.

![](/images/csdirector-cstruss/images/d-piecelabelconsolidation.png)
 |


**Accessing**

1. In the main **Project List** window, select **Presets**.
2. Select **Piece Labeling and Sequencing**, and information displays to the right.
3. In the **Preset Manager** window, add and revise information as needed.


**Related Topics**

- [Presets](/csdirector-cstruss/help-center/director-online-help/presets/d-presetssettings)
- [Batch Processing](/csdirector-cstruss/help-center/director-online-help/batching/d-batchprocess)
- [Batching Example - No Label Consolidation, Saw Files Consolidate at the Project Level](/csdirector-cstruss/help-center/director-online-help/batching/d-batchingexample1-nolabelconsolidationsawfilesconsolidateatproject)
- [Batching Example - Consolidation of Labels and Saw Files Across the Project](/csdirector-cstruss/help-center/director-online-help/batching/d-batchingexample2-consolidatelabelssawfilesacrossproject)
- [Batching Example - No Label Consolidation, Saw Files Consolidate Per Truss](/csdirector-cstruss/help-center/director-online-help/batching/d-batchingexample3-nolabelconsolidationlabelssawfilesconsolidatepertruss)
- [Batching Example - Consolidation of Saw File per Group, Consolidation of Piece Label per Truss with Number Restart per Group R1, B1, W1](/csdirector-cstruss/help-center/director-online-help/batching/d-batchingexample4-consolidatesawfilepergroupconsolidatepiecelabelpertruss)
- [Batch Processing Troubleshooting](/csdirector-cstruss/help-center/director-online-help/batching/d-batchprocesstroubleshooting)