Description
Dead load overrides should only be used when the actual dead load on the truss is calculated and the final dead loads applied to the truss will exceed the value entered.
Design Practices
The dead load used in determining wind uplift may not exceed the minimum expected actual weight of the materials.
If the minimum expected actual weight of materials is not known, the nominal design dead load must be reduced by 60% (0.60) of its original value when determining wind uplift; the dead load overrides should not be used when actual dead load is not known or calculated.
Required Actions
Ensure that the sum of the dead loads entered in the Overrides field on the Wind Load Dialog for the TC Dead Ld and BC Dead Ld is less than 10 psf. Ideally, these loads should reflect dead load values that have been calculated for the materials present, or reflect the minimum dead loads that will be applied to the truss at all times during its lifespan.